First Ammonia says its 2026 final investment decision is still on track, even after Danish technology company Topsoe terminated a 100 MW electrolyzer supply agreement for its Port of Victoria, Texas project on March 26, 2026. The split puts supplier risk in the green ammonia space squarely in the spotlight, and how quickly First Ammonia secures a new supplier will determine whether that confidence holds.
>> In Other News: History Written As CCS Technology Starts Operating On Board FPSO
The two companies go back to September 2022, when they announced the world's largest-ever electrolyzer reservation agreement, covering up to 5 GW of solid oxide electrolysis cell (SOEC) technology. Formal supply and service agreements covering the first 100 MW of SOEC modules were signed in 2024, kicking off fabrication at Topsoe's factory in Herning, Denmark.
By March 26, 2026, it was over. Topsoe cited missed project milestones as the reason, noting it had extended deadlines multiple times at First Ammonia's request before pulling out. Topsoe also confirmed it is conducting a broader review of its SOEC technology at industrial scale, expected to conclude by the end of Q2 2026, while remaining committed to a separate 50 MW offtake agreement with Forestal (pv-magazine, March 2026).
First Ammonia pushed back firmly on that framing, arguing that the supplier exit will not affect its FID schedule this year.
The project has real structural groundwork behind it. The Texas Commission on Environmental Quality issued a draft air permit for the Port of Victoria facility in March 2025, confirming that projected emissions fall within state and federal standards. In January 2025, Worley was awarded the FEED contract for the facility, with a completion target of Q1 2025. Notably, construction had been expected to begin in 2025, but the Topsoe termination means that timeline has shifted.
On the commercial side, German energy major Uniper has been an official project partner since October 2023, lined up to purchase green ammonia for industrial customers in North America and Europe. A Series B funding round from Mercuria Holdings and Tokyo-based Manies Group has been committed toward advancing the project to FID.
Worth noting: First Ammonia originally targeted FID for mid-2024, then pushed it to 2026. The Topsoe exit adds pressure on an already delayed timeline.
"Clean ammonia is essential in reducing emissions across hard-to-abate sectors, and Worley's capabilities are vital for enabling decentralized, electric ammonia production."
Joel Moser, CEO, First Ammonia (January 2025)
>> RELATED: 14 Green Hydrogen Projects Reshaping America's Energy Future
First Ammonia's design was built specifically around SOEC technology. Waste heat from the ammonia synthesis loop feeds back into the electrolysis process, cutting electricity consumption compared to conventional PEM or alkaline systems. That efficiency advantage is central to the project's cost model.
Finding a direct replacement will take time. First Ammonia has not yet named a new electrolyzer supplier, and that announcement will be the clearest signal the market watches. Meanwhile, Topsoe's SOEC industrial-scale review, due by end of Q2 2026, could also reshape which supplier options are realistically available.
| Electrolyzer Type | Key Advantage | Ammonia Integration |
|---|---|---|
| SOEC (Solid Oxide) | Highest efficiency via waste heat integration; 30% more energy efficient than conventional electrolyzers | Optimal, designed into First Ammonia's process |
| PEM (Proton Exchange Membrane) | Fast response to variable renewables; commercially proven at scale | Compatible but no heat integration benefit |
| Alkaline | Lowest cost at large scale; mature technology | Compatible with standard integration |
The commercial case for this project remains compelling. Each 100 MW module at Port of Victoria would produce up to 100,000 metric tons of green ammonia annually, avoiding 180,000 to 240,000 metric tons of CO2 compared to conventional grey ammonia production (First Ammonia/Uniper, October 2023). At full buildout, First Ammonia has outlined potential capacity of 5 million metric tons per year by 2035.
"We want to prove that a modular approach to building green ammonia plants is not only possible, but optimal."
Kevin Barnes, Global Head of Construction and Technology, First Ammonia
The sector is growing fast. 2.2 million metric tons per annum of active low-carbon hydrogen capacity was operational globally as of February 2026, across 460+ projects (GlobalData, February 2026). That number was just 104 projects in 2020. Total global hydrogen production capacity could reach 82.3 million metric tons per annum by 2030, though only 2% is currently operational (GlobalData, 2026).
Three signals matter most over the coming months. First: a new electrolyzer supplier announcement, and whether it preserves the SOEC-based heat integration that was central to the project's efficiency case. Second: whether First Ammonia can formalize that new supplier relationship quickly enough to keep the 2026 FID window open. Third: the outcome of Topsoe's SOEC industrial-scale review in Q2 2026, which could affect the broader supplier landscape.
The green ammonia industry needs projects like Port of Victoria to succeed. First Ammonia has the permits, the FEED, the offtake partner, and the funding foundation. The supplier pivot is a real setback, but the project's underlying foundations remain intact. The next announcement will tell us how much ground was actually lost.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🍁 Ballard Buys GeoPura for $400M in Hydrogen Power Push ⛽ XCF Global Begins Producing Renewable Fuels at New Rise Renewables Reno 📈 WoodMac: CCUS Growth Continues Despite Project...
Inside This Issue ⚡ Airbus and MTU Aero Engines to Create a Joint Venture to Develop a Fully Electric Hydrogen Fuel Cell Engine 🌳 Something Weird Is Going on with the 66 Billion Trees China Plante...
Inside This Issue ⚡ SB 1350: California Makes Hydrogen Power Count as Clean 🏭 Europe's Carbon Capture Push Shifts From Ambition To Delivery At CCSA EU Conference 2026 🍁 Canada and Alberta Tie New ...
MAX Power Mobilizes for Commercial Validation Program at Canada’s First Natural Hydrogen Discovery
Multi-well program commences early next week at Lawson Complex following 3D seismic and independent modelling as MAX Power advances toward potential commercial-scale Natural Hydrogen development. ...
Montana Renewables Collaborates with Gulfstream for Low Emissions Testing
GREAT FALLS, Mont., July 8, 2026 /PRNewswire/ -- Montana Renewables, LLC (MRL) is proud to have collaborated with Gulfstream Aerospace Corp. and its partners as the exclusive fuel supplier for rece...
XCF Global Begins Producing Renewable Fuels at New Rise Renewables Reno
Initial renewable diesel production marks commissioning and restart milestone as facility advances toward planned sustainable aviation fuel configuration Marks transition to expected revenue-gener...
Carbon Capture Project Gains Support
Deep Sky seeks to build on Alberta success as it pitches province on ‘economic opportunity for Manitoba on a global scale’ WINNIPEG — A direct air carbon capture facility proposed for southwestern...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.