Published by Todd Bush on November 12, 2025
Brossard, Quebec – TheNewswire – November 12, 2025 – CHARBONE CORPORATION (TSXV: CH; OTCQB: CHHYF; FSE: K47) ("CHARBONE" or the "Company"), a North American producer and distributor specializing in clean Ultra High Purity (UHP) hydrogen and strategic industrial gases, is pleased to confirm that the construction schedule at its Sorel-Tracy site remains fully on track, with the equipment installation phase set to begin in the coming days.
The civil construction works, which began on October 27, 2025, are now completed, including foundation preparation and all required technical infrastructure for the reassembly of the main production systems. All major components delivered in October will be installed on-site before the end of the month, keeping the project on pace for the planned commissioning in November 2025 of Phase 1a.
>> In Other News: [x](x)
“The fact that our schedule remains perfectly on track reflects the efficiency and dedication of our teams, along with the exceptional collaboration of our technical and municipal partners,” said Dave B. Gagnon, CEO of CHARBONE CORPORATION. “We are now entering the most tangible phase of the project — the installation of the equipment — marking the transition toward testing and commissioning of our first clean UHP hydrogen production module in Quebec.”
The Sorel-Tracy site represents CHARBONE’s first local and modular clean hydrogen production facility in Quebec, aligning with the Company’s broader vision to develop a decentralized North American network for the production and distribution of clean and strategic industrial gases. For more information on the Company’s five-phased approach and economics for CHARBONE’s modular facility, please see the latest investor presentation on the Company’s website.
CHARBONE is an integrated company specializing in clean Ultra High Purity (UHP) hydrogen and the strategic distribution of industrial gases in North America and Asia-Pacific. Through a modular approach, the Company is building a distributed network of green hydrogen production plants while diversifying revenues via helium and specialty gas partnerships. This disciplined model reduces risk, enhances flexibility, and positions CHARBONE as a leader in the transition to a low-carbon future. CHARBONE is listed on the TSX Venture Exchange (TSXV: CH), the OTC Markets (OTCQB: CHHYF), and the Frankfurt Stock Exchange (FSE: K47). Visit www.charbone.com.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🍁 North Star Carbon Removal Project Selected by Government of Canada for Landmark Carbon Removal Procurement Program 🚢 Trafigura Ship Fuel Venture Isn't Rushing Into Alternative ...
Inside This Issue 🔋 Molten Industries Commissions World’s First Plant to Produce Battery-Grade Graphite from Natural Gas 🪨 European Commission Presents Draft Rules for Certifying Enhanced Rock Wea...
Inside This Issue ⚙️ GE Vernova’s Greenville Lab Moves Turbines Closer to 100% H2 🚗 Geely Holding Announces Evsa’s Global Launch at COP31 🚢 Ethanol Blends Run Successfully in Pilot Marine Engine T...
Nordic Ren-Gas Reaches Final Investment Decision on Tampere E-Methane Facility
Nordic Ren-Gas (Ren-Gas), a Taaleri development capital investment since December 2025, has reached the Final Investment Decision (FID) on its renewable e-methane production facility in Tampere, Fi...
COP31 Draft Drops Fossil Fuel Language as Talks Near Deadline
Greenpeace activists unveil a three-dimensional floor installation titled “Don’t Fall for Fossil Fuels” at the U.N. Climate Change Conference (COP31) in Antalya, Turkey, Novembe...
Download the release PowerCell Group has, through its U.S. subsidiary PowerCell Inc., signed an agreement worth SEK 440 million with an established U.S.-based electric cooperative for a utility-sc...
Integrated solution simplifies execution and reduces project risk to support the production of up to 140,000 MTPA of eSAF CHARLOTTE, N.C., Nov. 18, 2026 — Phelan Green, through its clean fuels sub...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.