Published by Todd Bush on November 11, 2026
The U.S. Environmental Protection Agency (EPA) has posted the Class VI permit application for Carbon TerraVault VIII. The filing reveals a five-well carbon storage hub now in administrative review. EPA Region 9 updated the listing on October 23, 2026. The next milestone is an EPA completeness determination, which opens technical review.
>> In Other News: [x](x)
EPA Region 9 added CTV VIII to its public Class VI application table, with materials last updated on October 23, 2026. The entry confirms five proposed injection wells and a multi-source hub design.
The applicant is California Resources Corporation (CRC), a Long Beach, California energy and carbon management company. It develops storage through Carbon TerraVault, its carbon capture and storage business. EPA records show the application was submitted on September 30, 2026.
CRC has proposed about 57 million metric tons of total storage capacity for the project. That figure places CTV VIII alongside earlier Carbon TerraVault vault filings across the San Joaquin and Sacramento basins.
EPA lists the exact location and the proposed injection volume or rate as confidential business information (CBI). Federal rules under 40 C.F.R. Part 2, Subpart B govern how EPA handles those claims.
CRC's Class VI storage applications cover sites in California's San Joaquin and Sacramento basins.
CTV VIII proposes five injection wells, the fewest among CRC's three hub applications on EPA's Region 9 table. EPA describes each hub as collecting CO2 from multiple sources over time.
Every Class VI well needs its own individual application and permit, according to EPA. That means CTV VIII involves five separate well permit decisions.
| Project | Submitted | Location | Wells | Proposed Volume | EPA Status |
|---|---|---|---|---|---|
| CTV VI | July 31, 2024 | Fresno County | 7 | 101.5 million metric tons over 30 years | Administratively complete, September 20, 2024 |
| CTV VII | February 26, 2026 | South Coles Levee, Kern County | 6 | 27.4 million metric tons over 19 years | Administrative review |
| CTV VIII | September 30, 2026 | Confidential | 5 | Confidential (CBI) | Administrative review |
Completeness timing has varied across CRC filings. CTV VI moved from submission to administrative completeness in 51 days during 2024, based on EPA Region 9 records. CTV IV took 69 days in 2023.
Monitoring plans also become binding at the draft stage. EPA writes the Class VI Project Plans into each draft permit as enforceable conditions, a step that shapes long-term CO2 monitoring programs at storage sites.
"I'm honored to be able to help provide innovative decarbonization technology solutions like Carbon TerraVault that's going to revolutionize how we combat climate change here in California."
Juan Campos, Vice President, Health, Safety and Environmental, and Sustainability, California Resources Corporation
CTV VIII must clear five EPA review stages before any well can be permitted. Construction approval and a final injection authorization follow after that.
EPA's Class VI dashboard lays out the review sequence:
CRC listed further conditions when it received its first Class VI permits in December 2024. They included a 30-day window for petitions to EPA and EPA approval of completed wells and surface facilities. A final EPA authorization to inject came last.
EPA describes a hub as a project that collects CO2 from multiple sources over time. Carbon TerraVault has also pursued a California direct air capture hub through a consortium selected for U.S. Department of Energy funding.
EPA says review timing depends on project complexity and the quality of the submitted application. The first public signal will be a status change on the Region 9 listing.
Carbon TerraVault VIII's proposed five-well carbon storage hub remains in EPA administrative review as of the October 23, 2026 listing update. The timeline shows the regulatory and pre-injection stages that must follow before CO2 injection can begin.
>> RELATED: Conestoga Energy Submits Class VI Carbon Capture & Sequestration Permit Application to EPA Region 7
EPA had Class VI applications pending for 44 projects, covering 142 individual wells, as of September 2026, according to the Congressional Research Service. Filed after that count, CTV VIII adds five more wells.
CRC holds an 88% share of California Class VI wells, according to its third-quarter 2026 investor presentation. The same deck puts its share of wells under EPA-led review nationwide at 36%.
Permit volumes keep growing elsewhere too. Decarbonfuse tracked how CCS permits climbed to 106 earlier this year. States such as Wyoming have also issued their own Class VI permits.
Class VI injection wells require EPA-approved construction before any CO2 can be stored underground.
Carbon storage is drawing investment beyond California too. Decarbonfuse has covered deals ranging from industrial capture agreements in Mississippi to public CCS investment in Alberta.
"Carbon capture, utilization, and storage is a critical piece of California's climate solutions puzzle and an important tool we're counting on to help achieve carbon neutrality."
Lauren Sanchez, Chair, California Air Resources Board
The California Air Resources Board (CARB), the state's climate and air quality regulator, counts storage among its carbon neutrality tools. Federal Class VI review by EPA remains the gate for every CTV well in the state.
Local news report covers the start of CO₂ injection at California Resources Corporation’s Carbon TerraVault I project in Kern County, California’s first operational carbon storage site.
The next CTV VIII milestone is EPA marking the application administratively complete on its Region 9 table. That status opens technical review of all five proposed wells.
EPA refreshes posted application materials as reviews advance, as the CTV VI and CTV VII listings show. Storage builds elsewhere offer a preview, including Occidental's STRATOS direct air capture project.
Where is Carbon TerraVault VIII located?
EPA lists the CTV VIII location as confidential business information. The project is filed with EPA Region 9, which reviews Class VI applications in California.
How many injection wells does CTV VIII propose?
The EPA listing shows five proposed Class VI injection wells. Each well requires its own individual EPA permit.
What does administrative review mean for a Class VI application?
EPA checks whether the application package is complete before technical review begins. Once EPA confirms completeness, it evaluates the site, wells, and project plans in detail.
For ongoing coverage of carbon removal, BECCS, and corporate CDR procurement, subscribe to Decarbonfuse.com.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🌽 The Andersons Bets $915M on Low-Carbon Ethanol Plants 🌐 Rad Web Hosting Announces Fossil-Free Internet by 2030 Manifesto, Commits 1% of Revenue to Carbon Removal 💶 EU Earmarks ...
Inside This Issue ✅ Verra Approves First Credits Under CCS Methodology ⚡ Houston-Based Transition Industries Signs EPC Deal for 210 MW Electrolyzer at Pacifico Mexinol 🏗️ Investing in Wyoming’s In...
Inside This Issue ⚖️ Court Sets Aside Kern County Approval of California’s First Carbon Storage Project, Carbon TerraVault I 🌲 The Integrity Council Approves Methodologies for Coal Transition and ...
Carbon TerraVault VIII's Five-Well Hub Enters EPA Review
The U.S. Environmental Protection Agency (EPA) has posted the Class VI permit application for Carbon TerraVault VIII. The filing reveals a five-well carbon storage hub now in administrative review....
Survey to add new gravity measurements west of the Cloverleaf target and within the eastern block ahead of 3D inversion and 2D seismic-profile modelling VANCOUVER, British Columbia, Nov. 10, 2026 ...
Greene Tweed Introduces PFAS-Free Sealing Material Built for Hydrogen and CCUS Reliability
EPM 893 reduces sealing tradeoffs by combining low-temperature performance, decompression resistance, and chemical compatibility LANSDALE, PA, UNITED STATES, November 10, 2026 /EINPresswire.com/ -...
Aemetis Biogas Receives CARB Approval for Six Dairy RNG Pathways
CUPERTINO, Calif., Nov. 10, 2026 (GLOBE NEWSWIRE) -- Aemetis, Inc. (NASDAQ: AMTX), a renewable natural gas and biofuels company, announced today that the California Air Resources Board (CARB) has a...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.