In mid‑March, the filling of the two caverns at the H2CAST Etzel pilot project was successfully completed by the leading consortium partners STORAG ETZEL and Gasunie with approximately 90 tonnes or 1 million standard cubic metres of hydrogen. By emptying the 200th trailer the full hydrogen amount for H2CAST pilot was in place.
Further milestone in the conversion of existing caverns for hydrogen use at Etzel achieved as planned.
Approximately 90 tonnes, or 1 million standard cubic metres of hydrogen, have been safely injected by STORAG ETZEL and project partner Gasunie into the caverns.
The unique pilot test plant to test efficiency of hydrogen purification processes and multi-cyclic cavern operation is under-construction and will be ready for the first tests in 2026.
The H2CAST consortium aims to demonstrate the feasibility of underground hydrogen storage.
“Following the conversion of the caverns and continuous monitoring of tightness and integrity, another important milestone has been achieved in line with the high safety standards customary at the Etzel site,” said Carsten Reekers, Project Manager H2CAST Etzel at STORAG ETZEL.
>> In Other News: Climefi Structures The First Publicly Announced Transaction For CRCF Carbon Removal Units
Particular attention is now focused on the completion of the above‑ground facilities for gas purification, compression and gas quality monitoring, which are being newly constructed for hydrogen. Various gas purification methods and their efficiency will be tested. Preparations for this are already well advanced.
“Gasunie is confident that together with our employees and partners we will master this next step as a team. Being able to rely on the skilled expertise within the H2CAST partners we believe that this project will guide and strengthen the hydrogen path.”, states Eddy Kuperus, Business Development Manager Hydrogen Storage at Gasunie.
Carsten Reekers: “The knowledge that we gain from the H2CAST pilot project will contribute to the future underground hydrogen storage. In recent years since early 2022, valuable experience has already been gained. This supports the statement that there is a high degree of comparability with natural gas storage and that the existing caverns at Etzel are suitable for hydrogen storage.”
The injection forms part of the research and development project ‘H2CAST Etzel’, which develops the technical implementation of hydrogen storage in salt caverns. “The filling of the test cavern with hydrogen and the associated procurement process for the H2CAST Etzel research project highlighted the early stage of development of the German market. At the start of filling in 2023, high‑pressure trailers and filling stations (>200 bar) were only available to a very limited extent. Combined with the lack of local production – with some deliveries over distances of up to 1,000 km – this resulted in a high proportion of hydrogen costs.”
“Meanwhile, the market has evolved, allowing us to secure a delivery from a nearby hydrogen producer during the project period—significantly lowering both logistics and production costs. Looking ahead, once Etzel is connected to the approved national hydrogen ‘core network’, the site will become a key hub for hydrogen storage within the future energy system,” said Project Manager Reekers.
“Our gas operations specialists have the hydrogen filling process steps safely under control. Handling of the new energy carrier is carried out professionally and routinely on a day‑to‑day basis,” Reekers continued.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🌐 Frontier Secures $915 Million From Google, Anthropic and Tech Buyers to Scale Permanent Carbon Removal 🧪 IEA Cuts 2030 Clean Hydrogen Outlook by 40% as Investment Stalls 🦘 Aust...
Inside This Issue 🐄 Circularity Fuels Converts Raw Dairy Biogas to Jet Fuel in World First End-to-End Pilot 🌍 Puro.earth Hits Milestone With 1 Million Retired Carbon Removal Certificates 🍁 Alberta...
Inside This Issue ✈️ American Airlines and Google Sign Record 35M-Gallon SAF Deal 🛡️ Isometric Launches CORSIA Insurance RFP With Howden 🍁 TKMS, Heirloom Carbon Technologies and Thyssenkrupp Calv...
Record removals signed: Climeworks Solutions has signed 14 new carbon removal deals in its strongest half-year to date, totaling approximately 450,000 tons of carbon dioxide removal (CDR) across a...
Honeywell to Power Sustainable Aviation Fuel and Renewable Diesel Production
Honeywell will provide modular processing technology and automation systems for Acelen Renewables’ biofuels facility in Brazil, supporting large-scale production of sustainable aviation fuel and re...
This is the first time in the world that fuel has been produced from certified soybeans without impacting land-use change under the international ISCC CORSIA PLUS protocol; the product has the pote...
JERA Co., Inc. (JERA), a global energy leader and Japan’s largest power generation company, today announced that it has entered into time charter agreements with NYK Bulkship (Asia) Pte. Ltd (“NYK”...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.