CF Industries started civil construction on the Blue Point One ammonia complex in August 2026, after state and federal permits arrived in July. That is the moment a project stops being a plan. It becomes a commitment with a schedule, a contractor on site, and capital flowing at scale. For the blue ammonia market, this milestone changes the risk profile of everything that depends on Blue Point delivering by 2029.
Between FID in April 2025 and August 2026, Blue Point was advancing through engineering, equipment procurement, and permitting. Real capital was being deployed, but the project still carried pre-construction risk. The permits could have been delayed. The contracting structure could have frayed. Partners could have reassessed.
None of those things happened. Instead, both Louisiana state regulators and the U.S. Army Corps of Engineers issued civil construction permits in July 2026, on schedule. That removed the last external gate between FID and the build phase.
The project now enters a different risk category. Cost overrun and schedule delay are still live risks on any construction project of this scale. But regulatory reversal, partner withdrawal, and permitting failure are not. Three equity partners have committed capital that is already being drawn. A billion-euro EPC contract is in execution. That is a qualitatively different risk profile from any stage that came before.
With a Technip Energies EPC contract exceeding one billion euros in execution, Blue Point has moved from pre-construction risk into active build-phase risk.
Capital flows confirm the shift. Through the first half of 2026, $143 million of the joint venture's $600 million annual capex had already been deployed on engineering and procurement. That is real money from three equity partners, not projections. JERA and Mitsui fund 60% of joint venture spend at their respective ownership ratios. Their contributions were flowing before a single shovel of civil dirt was turned in August.
"We believe the Company is positioned extremely well in the near- and longer-term, with our premium-grade North American asset base, disciplined strategic growth opportunities, including Blue Point, and strong balance sheet."
Chris Bohn, President and CEO, CF Industries Holdings, Inc., August 2026
The 2029 target has not changed, but what supports it has changed materially. The project is now running on a construction schedule, not a development timeline. Technip Energies holds the EPC contract and is accountable to milestones. Construction delays on a project this size are common, but they are managed differently once physical work is underway.
The more significant data point is what is happening in Japan at the same time. JERA is not waiting for Blue Point to deliver. It has already contracted IHI Corporation for four liquid ammonia storage tanks at its Hekinan Thermal Power Station. Each tank is approximately 60 meters in diameter and 40 meters in height. Combined capacity: 160,000 metric tonnes. Construction of those tanks is actively in progress as of early 2026, with commercial co-firing of 20% ammonia targeted for fiscal year 2029.
That parallel build matters enormously. JERA is spending capital on receiving infrastructure timed to Blue Point's delivery date. A buyer who is constructing the import terminal is not a buyer who is hedging their exposure. That synchronized investment on both sides of the Pacific makes the 2029 timeline a shared operational target, not just a CF Industries aspiration.
>> RELATED: Japan Bets $4B on Louisiana Ammonia in Gulf Coast Shift
JERA is already building the Hekinan ammonia storage tanks timed to Blue Point’s 2029 delivery, locking in the offtake side of the supply chain.
The sequestration pathway is the one leg of the Blue Point supply chain that does not yet have a final regulatory clearance in hand. 1PointFive, an Occidental subsidiary, holds the 25-year CO2 offtake agreement for approximately 2.3 million metric tonnes per year. Its Pelican Sequestration Hub in Livingston Parish has taken FID and is in development. But Louisiana's Class VI permitting process, which governs underground CO2 injection wells, has not yet issued a final permit for the Pelican site.
Louisiana received EPA Class VI primacy in December 2023, meaning the state now runs its own permitting process rather than waiting for a federal queue. That is a meaningful advantage. But as of mid-2026, Louisiana had approved only one Class VI application. The Pelican Hub's application remains under state review.
The CO2 pipeline connecting Blue Point to the Pelican Hub is approximately 50 miles long. Enbridge Inc. will build and operate it through a 50/50 joint venture with 1PointFive, finalized in September 2025. Pipeline construction and Class VI well permitting are parallel tracks. They do not need to be complete before ammonia plant construction starts. But they do need to be complete before startup in 2029. The Pelican Hub's permitting progress is the piece of the Blue Point supply chain that still carries real forward uncertainty.
What construction of the ammonia plant does do is lock in the sequestration timeline. 1PointFive cannot miss 2029 without consequence. A 25-year, approximately 2.3-million-tonne-per-year CO2 contract is an anchor customer relationship. The Pelican Hub needs Blue Point as much as Blue Point needs Pelican.
The comparison table below shows why Blue Point reaching active construction is commercially significant. The other headline US projects in this space have not reached the same milestone.
| Project | Location | Status (Aug 2026) | Execution Risk |
|---|---|---|---|
| Blue Point One (CF / JERA / Mitsui) | Ascension Parish, Louisiana | Civil construction underway, August 2026 | Build-phase: schedule and cost |
| Louisiana Clean Energy Complex (Air Products) | Darrow, Louisiana | Cancelled June 30, 2026 ($2.9B write-down) | Project terminated |
| ExxonMobil Baytown Blue Hydrogen | Baytown, Texas | Paused, late 2025 | Contingent on 45V policy resolution |
| CF Industries Donaldsonville CCS | Donaldsonville, Louisiana | CCS operational since 2025 | Operational since 2025. Adjacent infrastructure for Blue Point |
Air Products took a $2.9 billion charge to exit the Louisiana Clean Energy Complex. ExxonMobil paused Baytown citing insufficient offtake commitments. Both projects carried the kind of pre-construction risk that Blue Point has now cleared. Blue Point is in the ground while its closest US competitors are not. That changes how Japanese offtakers, investors, and competing producers read North America's near-term blue ammonia export capacity.
For Asian industrial buyers with 2029 co-firing targets, there is now one project under active construction that can realistically meet that date. That is not a general industry observation. It is the specific position Blue Point now occupies.
Louisiana's Gulf Coast gives Blue Point access to natural gas supply, established pipeline networks, and deepwater export infrastructure already operational at CF Industries' adjacent Donaldsonville complex.
Construction start is a milestone, not a finish line. The next three years will determine whether Blue Point actually delivers what the market is pricing in. There are four specific things worth tracking.
"By working together, we can unlock the potential of American manufacturing and energy production, while advancing industries that deliver high-quality jobs and economic growth."
Jeff Alvarez, President, 1PointFive Sequestration
Pelican Hub Class VI permit. Louisiana's state regulator needs to issue a final injection well permit for the Pelican Sequestration Hub before startup. The state program is active and has clear timelines. But it has also issued only one final Class VI permit to date. Any sustained delay here would create pressure on the 2029 CO2 sequestration readiness.
Construction cost adherence. The joint venture budget is approximately $4 billion for the ammonia facility. CF Industries' Q2 2026 earnings called disclosed that 2026 joint venture capex is projected at $600 million, funded pro-rata by all three partners. The next several quarters of capex reporting will show whether the project is tracking to budget or drifting. CF Industries has flagged that costs could exceed current estimates.
Mitsui's Hokkaido supply chain. Mitsui plans to supply 280,000 metric tonnes annually to Hokkaido Electric Power's Tomatouatsuma Thermal Power Station, with that supply chain targeted by early 2031. The Tomakomai ammonia import hub in Hokkaido is in development. Its progress is a secondary indicator of whether the full Blue Point offtake stack is coming together on schedule.
45Q credit continuity. CF Industries claimed approximately $43 million in 45Q tax credits in the first half of 2026 from its existing Donaldsonville CCS operations. Blue Point's approximately 2.3 million metric tonnes of annual CO2 sequestration will generate substantially larger 45Q revenue once operational. The credit structure survived the One Big Beautiful Bill Act in July 2025 largely intact. Any future policy change that alters 45Q terms would directly affect Blue Point's economics at scale.
Four parallel tracks must each reach readiness by 2029 for Blue Point One to deliver its first commercial ammonia shipment to Japan.
The blue ammonia thesis has been debated at the policy and investment level for years. Blue Point is now the live test of whether it works in practice.
By 2029, the market will know whether a $4 billion ATR ammonia plant with more than 95% CO2 capture can be built on schedule. It will know whether cost tracked to budget and whether the Pelican Hub delivered on time. It will know whether the Pelican Hub's Class VI permitting completes in time for first injection. It will know whether JERA's Hekinan terminal receives its first cargo from Louisiana and whether the 20% co-firing milestone holds.
Each outcome carries real information for buyers, developers, and governments still deciding whether to commit to the North American blue ammonia supply chain. Construction starting in August 2026 is the point from which all of that gets answered.
Watch CF Industries' quarterly capex disclosures, Louisiana's Class VI permit pipeline, JERA's Hekinan terminal commissioning updates, and the Tomakomai hub timeline. Those four data streams will show whether the full supply chain is converging on 2029 or beginning to slip.
What specifically started in August 2026, and what was already underway before that?
August 2026 marks the start of civil construction activities at the ammonia plant site, authorized by permits issued by Louisiana regulators and the U.S. Army Corps of Engineers in July 2026. Engineering, equipment procurement, and pre-construction work had been underway since 2025. By the end of June 2026, $143 million of the joint venture's $600 million 2026 capex had already been spent, per CF Industries' SEC filing.
Is the carbon storage infrastructure ready for when the plant starts up?
Not yet, but it is on a parallel track. 1PointFive's Pelican Sequestration Hub has taken FID and is in development. Enbridge is building the approximately 50-mile CO2 pipeline connecting Blue Point to the hub. Louisiana's Class VI injection well permit for the Pelican site has not yet been issued but is under state review. The ammonia plant does not need that permit to build. It needs it by 2029 to operate with full CO2 capture.
What does Blue Point's construction start mean for the wider blue ammonia market?
Blue Point is the only large-scale blue ammonia project in North America currently under active construction. The Louisiana Clean Energy Complex was cancelled in June 2026. ExxonMobil's Baytown project is paused. That makes Blue Point's 1.4 million metric tonnes per year, targeted for 2029, the primary near-term source of US Gulf Coast blue ammonia export supply for Asian buyers with co-firing timelines.
For ongoing coverage of carbon capture, blue ammonia, and the US carbon storage buildout, subscribe to Decarbonfuse.com.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This News ⚡ IRS Expands and Extends 45Q Safe Harbor, Offering Long-Term Certainty to Carbon Capture Projects 🌊 South Korea Signs MoU for 320MW Green Hydrogen Complex 🌱 Senken and Carbonsate...
Inside This Issue 📋 GAO Report Flags Oversight Gaps in 45Q Carbon Capture Credit 💰 Google Opens 2026 R&D Awards Offering $6M+ for Carbon Removal and Superpollutant Research 🌍 NEOM Green Hydrog...
Inside This Issue 🪟 Cardinal Glass to Deploy World's First Carbon Capture System at Float Glass Plant 🔬 SunHydrogen's Solar-to-Hydrogen Modules Exceed 10% Efficiency in SPARC Testing, Advancing to...
NextChem will provide licensing, Process Design Package (PDP) and engineering services for the syngas section of Project Lion in North Queensland, leveraging its proprietary NX Circular™ Gasificat...
BERLIN, Aug. 17, 2026 /PRNewswire/ -- Senken today announces the largest biomass storage deal signed in Europe to date: a multi-year carbon removal offtake with Berlin-based Carbonsate covering 50,...
KBR Selected by ORNX for Low-Cost Ammonia Pre-FEED Study Supporting Landmark Morocco Project
HOUSTON, August 12, 2026 – KBR (NYSE: KBR) announced today that it has been selected by ORNX Green Hydrogen for the pre-front-end engineering design (Pre-FEED) phase of a world-scale, low cost ammo...
NEOM Green Hydrogen Megaproject Enters Commissioning Ahead of 2027 Start
Construction of the $8.5 billion NEOM Green Hydrogen Project is complete, with commissioning under way ahead of planned commercial operations in 2027 Construction work on the $8.5 billion NEOM Gre...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.