Alberta Now Pays CCUS Grants Before Projects Start Up

Published by Todd Bush on November 27, 2026

Alberta will now pay part of its 12% carbon capture grant while projects are still being built. The change to the Alberta Carbon Capture Incentive Program (ACCIP), announced November 19, 2026, also extends funding to 2035. The rate stays the same, but the cash now arrives sooner.

Before the update, operators waited until a facility was running before any grant money arrived. Developers now carry less of the build cost on their own balance sheets before start-up.

Key Facts

  • ACCIP covers 12% of eligible capital costs for new CCUS projects, with funding now running to 2035.
  • Part of the grant can now be paid during construction. Previously, payments began only after operations started.
  • Grants are paid annually after the previous year's eligible costs are verified. Alberta has not published an early-payment share.
  • Alberta projects CCUS could attract up to C$23 billion in investment and 17,000 jobs over the next decade.
  • Quest and the Alberta Carbon Trunk Line have stored more than 18 million tonnes of CO2 since 2015.
  • Seven of the 25 storage hub projects selected in 2022 have signed carbon sequestration agreements.

>> In Other News: CF Industries Holdings, Inc. Announces Agreement to Acquire Faustina Ammonia Production Facility from The Mosaic Company

What Did Alberta Change in ACCIP?

Alberta made three changes on November 19, 2026: earlier payments, a 2035 funding horizon and closer alignment with Ottawa's tax credit.

ACCIP covers 12% of eligible capital costs for new carbon capture, utilization and storage (CCUS) projects, according to the Government of Alberta. Eligible projects can now receive part of that grant during construction.

The updated program page says grants are paid annually after the previous year's eligible costs are verified. Neither the release nor the page sets the share that can arrive before operations.

Eligible sectors include oil and gas, power generation, petrochemicals and cement. Engineering studies, pilot projects and proof-of-concept work remain ineligible.

brian jean

"Alberta is already a global leader in carbon capture and storage, and we want to build on that advantage."

Brian Jean, Minister of Energy and Minerals, Government of Alberta

The update follows the November 2025 Canada-Alberta energy agreement. That deal committed the province to extend ACCIP in support of the Pathways carbon capture project.

How Does ACCIP Line Up With the Federal Tax Credit?

Alberta's 12% grant sits on top of Ottawa's refundable CCUS Investment Tax Credit, which covers 50% of most capture equipment through 2035. The province said the changes better align the two programs.

The federal credit pays 60% for direct air capture equipment and 37.5% for transport, storage or use. Those full rates apply through 2035, then drop by half from 2036 to 2040, according to EY.

Feature Alberta ACCIP Federal CCUS ITC
Type Provincial grant Refundable tax credit
Rate on capture equipment 12% of eligible capital costs 50% (60% for direct air capture)
Transport, storage or use 12% of eligible capital costs 37.5%
Full support runs through 2035 2035, then half rates 2036 to 2040
Payment timing Annual, after cost verification, now including construction Claimed through the tax system

Projects that send CO2 to enhanced oil recovery get half rates under the federal credit. CTV News reported those at 25% for capture equipment and 18.75% for transport, storage and use.

Both programs also work alongside the $1.2 billion carbon contracts for difference that Canada and Alberta agreed to fund jointly.

Why Does Construction-Phase Funding Matter?

Earlier payments cut the capital developers must finance before a capture plant runs. Total eligible support stays at 12%.

Under the original design, grants arrived in three annual instalments starting after one year of operations, according to Bennett Jones. A multi-year build meant years of carrying costs before the first provincial payment.

Paying part of the 12% during construction narrows that gap.

mark plamondon

"Long-term certainty matters when companies are making major capital investment decisions."

Mark Plamondon, Executive Director, Alberta's Industrial Heartland Association

Alberta's Industrial Heartland Association promotes heavy industry investment in Canada's largest hydrocarbon processing region, northeast of Edmonton. It welcomed the 2035 extension on November 20, 2026.

carbon capture unit with steel columns and piping at an industrial facility in alberta

Capture units like this one are the capital-heavy equipment that ACCIP's construction-phase payments are meant to help finance.

Alberta projects CCUS could attract up to C$23 billion in new investment over the next decade, per its November 19 release. The province also projects up to 17,000 jobs over the same period.

Where Does Pathways Stand?

Pathways targets about 6 million tonnes per year of CO2 capture by the mid-2030s. Final agreements between the companies and both governments are still being negotiated.

The Oil Sands Alliance behind Pathways includes Cenovus, Canadian Natural, Suncor, Imperial and ConocoPhillips Canada. Its July 2, 2026 MOU with Ottawa and Alberta ties lower carbon costs to Pathways delivery.

The project would carry CO2 by pipeline from oil sands sites to a storage hub near Cold Lake. Under the no Pathways, no pipeline framework, it is linked to a proposed West Coast oil pipeline.

>> RELATED: Pathways CCS: What Still Has to Be Signed Before FID

The parties had targeted definitive agreements by November 15, 2026. That date passed without a signing, and executives have said they will take the time needed for the right deal, CBC News reported.

Shared CO2 transport and storage infrastructure is expected to operate by 2032, according to the federal government's MOU backgrounder.

Federal Energy Minister Tim Hodgson and Alberta Energy Minister Brian Jean take questions at the September 9, 2026 groundbreaking for Enhance Energy’s Origins carbon capture and storage hub near Clive, Alberta — set to become Canada’s largest CCS project when it begins operations in January 2027.

How Does the Rest of Canada's Carbon Management Pipeline Look?

Alberta's storage base keeps growing beyond Pathways. Quest and the Alberta Carbon Trunk Line have stored more than 18 million tonnes of CO2 since 2015, according to the Government of Alberta.

Seven of the 25 carbon storage hub projects Alberta selected in 2022 have now signed sequestration agreements with the province. One of them has already started injecting CO2.

Enhance Energy, the Calgary-based operator of the trunk line's storage site, broke ground on its Origins hub near Clive in September 2026. Origins is set to open in January 2027 with capacity to store up to 1.5 million tonnes a year.

co2 injection wellhead and pipeline at a carbon storage site on the alberta prairie

Storage hubs like Origins near Clive give new capture projects a place to send CO2 for permanent storage.

Carbon removal is growing too. Deep Sky, a Montreal-based carbon removal developer, began operations at Deep Sky Alpha in Innisfail in August 2025.

Alpha is designed to capture 3,000 tonnes of CO2 a year while testing several direct air capture technologies side by side. Federal support also reaches other regions, including clean energy funding in Atlantic Canada.

What Comes Next for Alberta CCUS?

Three items will shape how fast projects move from planning into construction.

  1. Program guidelines showing how much of the 12% grant can be paid before operations.
  2. Definitive Pathways agreements between Ottawa, Alberta and the five oil sands producers.
  3. More storage hub sequestration agreements beyond the seven already signed.

Frequently Asked Questions

Did Alberta increase the ACCIP grant rate?

No. The grant still covers 12% of eligible capital costs. The update lets part of it arrive during construction and extends funding to 2035.

How much of the grant is paid before a project starts operating?

Alberta has not published a share. Grants are paid annually after the previous year's eligible costs are verified.

Does ACCIP work with the federal CCUS tax credit?

Yes. ACCIP is designed to align with the federal credit, which covers 50% of most capture equipment and 60% for direct air capture through 2035.

For developers, the headline number is unchanged at 12%. The calendar is what got better, with cash now able to flow while steel goes up.

For ongoing coverage of carbon removal, BECCS, and corporate CDR procurement, subscribe to Decarbonfuse.com.

Icons/external Source

Add Comments

Subscribe to the newsletter

Icons/inbox check

Daily decarbonization data and news delivered to your inbox

Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.


Latest issues

View all issues

Company Announcements

Daily decarbonization data and news delivered to your inbox

Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.

Subscribe illustration